# | Metric | Definition | Traget Measure (45 Days After Go-Live) |
---|---|---|---|
1 | #Projects Created Vs Projects Approved | Projects Created - Count of the projects created in the MUKTASoft Projects Approved - Count of the projects which are identified and finalized by the ULB committee within 5 weeks since initiation of Pilot | 80% or 5 projects whichever is higher |
2 | #Estimates Approved Vs Projects Created | Estimate Approved - Count of estimates created and approved in the MUKTASoft against a project Projects Created - Count of the projects created in the MUKTASoft within 4 weeks since initiation of Pilot | 80% or 4 projects whichever is higher |
3 | #Work Orders Accepted Vs Estimates Approved | Work Order Accepted - Count of work orders issued and accepted by CBOs. Estimate Approved - Count of estimates created and approved in the MUKTASoft against a project within 3 weeks since initiation of Pilot | 80% or 3 projects whichever is higher |
4 | #Wage seekers engaged | Wage seekers engaged - Count of wage seekers engaged by the CBOs for the work orders accepted within 3 weeks since initiation of pilot. | 100% wage seekers registered for applicable work orders |
5 | #Muster Rolls Approved Vs Project Period In Weeks | Muster rolls Approved - Muster roll created and approved. Project Period (In Weeks) - Total period of all the accepted projects initiated within 4 weeks since pilot go-live | 50% or 5 muster rolls whichever is lower |
6 | Bill Created (INR) Vs Bill Paid (INR) | Bill Created - Total value of bills created and due for payment Bill Paid - Total value of bills cleared payments | Target to be decided based if and when JIT integration is completed within the pilot duration |