NOTE:
-
In these examples, there are 4 user-defined ENVs variables of directories: $E3SM_INPUTDATA, $E3SM_ROOT, $PROJECT_E3SM, for inputdata, e3sm model source codes, and root directory for cases and runs, respectively. USERS must have created these, and cloned both data and e3sm codes.
-
$E3SM_INPUTDATA is cloned repository of a few site-level full datasets to run offline ELM, from pt-e3sm-inputdata
-
Upon user's machine, $MACH_NAME is needed for E3SM. In these examples, 'mymac' for MacOS/linux, 'wsl' for Windows Subsystem for Linux, OR, 'cades' for a cluster in ORNL, may be directly used.
HERE we manually customize E3SM Land Model to run with option of 'CPL_BYPASS' (coupler_bypass), developed by Dr. Daniel Ricciuto at ORNL. This configuration will run offline ELM about 3 times
faster and vey-slightly different
results, although not bit-for-bit
There are 4-5 forms of this configuration, upon what meteorological dataset to drive the land model. We will demonstrate 1 of them as following: (1) 'site' - user-provided point metdata
, which is CPL_BYPASS version of ELM Example Case I. Point Mode
- STEP 1. Create a PTCLM case, with
--compset ICBxxxx
1) cd $E3SM_ROOT/cime/scripts
2) ./create_newcase --case $PROJECT_E3SM/cases/Test_elm-ICB1850CNPRDCTCBC --res ELM_USRDAT --mach $MACH_NAME --compiler gnu --compset ICB1850CNPRDCTCBC --walltime 06:00:00
- STEP 2. Configure the case created in STEP 1 (user-defined 1 point dataset, namely '1x1pt_US-Brw' from 1985-2015)
3) cd $PROJECT_E3SM/cases/Test_elm-ICB1850CNPRDCTCBC
4) ./xmlchange, (OR, vi env_run.xml)
--id CLM_USRDAT_NAME --val 1x1pt_US-Brw
ADDITIONALLY,
if 'accelerated spinup', you need to edit 'env_run.xml' as following:
--id CLM_FORCE_COLDSTART --val on
--id CLM_ACCELERATED_SPINUP --val on
--id CLM_BLDNML_OPTS --val '-bgc bgc -nutrient cn -nutrient_comp_pathway rd -soil_decomp ctc -methane -nitrif_denitrif'
(i.e. remove P limitation for ad_spinup)
By default, the model run on machine is upon some pre-configured PE setting. For an example, the case setup by now will run model on 1 node with 8 MPI Task. So that's not good for 1 PT model, so vi env_mach_pes.xml
as following so that model runs on 1 node with 1 MPI Tasks
6) vi env_mach_pes.xml
<entry id="NTASKS">
<type>integer</type>
<values>
<value compclass="ATM">1</value>
<value compclass="CPL">1</value>
<value compclass="OCN">1</value>
<value compclass="WAV">1</value>
<value compclass="GLC">1</value>
<value compclass="ICE">1</value>
<value compclass="ROF">1</value>
<value compclass="LND">1</value>
<value compclass="ESP">1</value>
</values>
<desc>number of tasks for each component</desc>
</entry>
OR,
./xmlchange NTASKS=1
IF PNETCDF is not available,
./xmlchange PIO_TYPENAME=netcdf
THEN, issue the following command:
7) ./case.setup
(./case.setup --clean FOR cleaning-up)
The above command may or may not be successful (mostly with errors relevant to missing input files). AND it's also missing of metdata and setting for CPL_BYPASS. So, modifying user_nl_elm
as following:
metdata_type = 'site'
metdata_bypass = '$E3SM_INPUTDATA/atm/datm7/1x1pt_US-Brw/cpl_bypass_full'
aero_file = '$E3SM_INPUTDATA//atm/cam/chem/trop_mozart_aero/aero/aerosoldep_monthly_1850_mean_1.9x2.5_c090803.nc'
CO2_file = '$E3SM_INPUTDATA//atm/datm7/CO2/fco2_datm_1765-2007_c100614.nc'
nyears_ad_carbon_only = 25
spinup_mortality_factor = 10
NOTE: (1)the last 2 options are optional, but which can accelerate spinup much better. (2) Those options are to instruct model read datasets from indicated directory or files. In this case, the 'metdata' is located in directory metdata_bypass
with filename all_hourly.nc
.
THEN, re-issue command ./case.setup
- STEP 3. Build the case from STEP 1-2
FOR CPL_BYPASS
, ONE more editing IS required before code compiling. Edit Macro.make
and Macro.cmake
under case directory as following (appending -DCPL_BYPASS
into CPPDEFS)
Macro.make:
CPPDEFS := $(CPPDEFS) -DFORTRANUNDERSCORE -DNO_R16 -DCPRGNU -DCPL_BYPASS
Macro.cmake:
set(CPPDEFS "${CPPDEFS} -DFORTRANUNDERSCORE -DNO_R16 -DCPRGNU -DCPL_BYPASS")
THEN, build the model:
8) ./case.build
(./case.build --clean #cleaning-up ALL E3SM model components
./case.build --clean lnd #cleaning-up LND component
./case.build --clean-all #cleaning-up ALL model components and External components)
- STEP 4. Run the case
./case.submit
NOTES:
*(a) the run direcory is:$PROJECT_E3SM/cases/Test_elm_ICB1850CNPRDCTCBC/run
*(b) The run length is 5 days, with monthly output, i.e. NO real data write out EXCEPT for restart files at the end.
*(c) If you'd like what-ever time-length of the simulation, editing env_run.xml
, for an example, like the following:
--id STOP_OPTION nyears
--id STOP_N 200
(These editing will let model run 200 years, with monthly outputs of default variables, AND will produce 2 restart files)
*(d) If simulation may not be finished in WALLCLOCK time, it will crash. Then have to editing env_run.xml
to resume run:
--id CONTINUE_RUN TRUE
NOTE: The unfinished run MUST have produced 2 restart files, .elm.r..nc, .cpl.r..nc. IF NOT, have to redo run from beginning, with smaller interval for producing restart files, like (retart file writing every 10 years):
--id REST_N 10
--id REST_OPTION nyears