Activity Selection Problem

The problem of scheduling sveral competing activities that require exclusive use of a common resource, with a goal of selecting a maximum-size set of mutually compatible activities.

Suppose we have a set S = {a1, a2, ..., an} of n proposed activities that wish to use a resource. Each activity ai has a start time si and a finish time fi, where 0 <= si < fi < infinity. If selected, activity ai takes place during hald-open time interval [si, fi). Activities ai and aj are compatible if th eintervals [si, fi) and [sj, fj) do not overlap. That is, if si >= fj or sj >= fi.

We assume that the activities are sorted in monotonically increasing order of finishing time:

f1 <= f2 <= ... <= fn

Greedy Approach

We start by thinking about a dynamic-programming solution, in which we consider several choices when determining which subproblems to use in an optimal solution.

We shall then observe that we need to consider only one choice (the greedy choice) and then when we make the greedy choice, only one subproblem remains.

We shall complete the process of developing a greedy solution by converting the recursive algorithm to an interative one.

Optimal substructrure of the activity-selection problem

Let's denote Sij the set of activities that start after activity ai finishes and finish before activity aj starts.

Suppose that we wish to find a maximum set of mutually compatibile activities in Sij, and suppose further than such a maximum set is Aij, which includes some activity ak. By including ak in an optimal solution, we are left with two subproblems:

  • Finding mutually compatible activities in set Sik.
  • Finding mutually compatible activities in set Skj.

Let Aik = Aij ^ Sik and Akj = Aij ^ Skj, so that Aik contains activities in Aij that finish before ak starts and Akj contains activities in Aij that start after ak finishes.

Thus, we have Aij = Aik U {ak} U Akj, and so the maximum-size set Aij of mutually compatible activities in Sij consists of |Aij| = |Aik| + |Akj| + 1 activities.

We can show that the optimal solution Aij must also include optimal solutions to the two subproblems for Sik and Skj. If we could find a set Bkj of mutually compatible activities in Skj where |Bkj| > |Akj|, then we could use Bkj rather than Akj, in a solution to the subproblem for Sij. We would have constructed a set of |Aik| + |Bkj| + 1 > |Aik| + |Akj| + 1 = |Aij| mutually compatible activities, which contradicts the assumption that Aij is an optimal solution. A symmetric argument applies to the activities in Sik.

This way of characterizing optimal substructure suggests that we might solve the activity-selection problem by dynammicp rogramming. If we denote the size of an optimal solution for the set Sij by c[i,j], then we would have the following recurrence.

c[i,j] = c[i,k] + c[k,j] + 1

If we did not know that optimal solution for the set Sij includes activity ak, we would have to examine all activities in Sij to find which one to choose.

c[i,j] = if Sij == empty => 0
c[i,j] = if Sij != empty => mak ak in Sij { c[i,k] + c[k,j] + 1 }

We could then develop a recursive algorithm and memoize it, or we could work bottom-up and fill in table entries as we go along. But we would be overlooking another important characteristic of the activity-seleciton problem what we can use to great advantage.

Making the greedy choice

What if we could choose an activity to add to our optimal solution without having to first solve all the subproblems? The greedy choice.

Intuition suggests that we should choose an activity that leaves the resource available for as many other activities as possible. Now, of the activities we end up choosing, one of them must be the first one to finish. Therefore, choose activity in S with the earliest finish time (if more than one has it, then any such activity). In other words, since the activities are stored in monotonically increasing order by finish time, the greedy choice is activity a1.

Choosing the first activity to finish is not the only way to think of making a greedy choice for this problem.

If we make the greedy choice, we haveo nly one remaining subproblem to solve, finding activities that start after a1 finishes.

Why don't we have to consider activities that finish before a1 starts? We have that s1 < f1 and f1 is the earliest finish time of any activity, and therefore no activity can have a finish time less than or equal to s1. Thus, all activities that are compatible with activity a1 must start after a1 finishes.

Let Sk = { ai in S : si > fk} be the set of activities that start after activity ak finishes. If we make the greedy choice of activity a1, then S1 remains as the only one subproblem to solve. Optimal substructure tells us that if a1 is in the optimal solution, then an optimal solution to the original problem consists of activity a1 and all the activities in an optimal solution to the subproblem S1.

Proving intuition correct

Theorem: consider any nonempty subproblem SK, and let am be an activity in Sk with the earliest finish time. Then am is included in some maximum-size subset of mutually compatible activities of Sk.

Proof: Let Ak be a maximum-size subset of mutually compatible activities in Sk, and let aj be an activity in Ak with the earliest finish time. If aj = am, we are done, since we have shown that am is in some maximum-size subset of mutually compatible activities of Sk.

If aj != am, let the set A'k = Ak - {aj} U {am} be Ak but substituting am for ak. The activities in A'k are disjoint, which follos because the activities in Ak are disjoint, aj is the first activity in Ak to finish, and fm <= fj. Since |A'j| = |Ak| we conclude that A'k is a maximum-size subset of mutually compatible activities of Sk, and it includes am.

Top-down design

Al algorithm to solve the activity-selection problem does not need to work bottom-up, like a table-based dynamic programming algorithm. Instead, it can work top-down, choosing an activity to put into the optimal solution and then solving the subproblem of choosing activities from those that are compatible with those already chosen.

Greedy algorithms typically have this top-down design: make a choice and then solve a subproblem, rather than the bottom-up technique of solving subproblems before making a choice.

Recursive greedy algorithm

The procedure RECURSIVE_ACTIVITY_SELECTOR takes start and finish times of activities, represented as arrays s and f, the index k that defines the subproblem Sk it is to solve, and the size n of the original problem. It returns a maximum-size set of mutually compatible activities in Sk. We assume that the n input activities are already ordered by monotonically increasing finish time.

In order to start, we add the ficticious activity 0 with f0 = 0, so that subproblem S0 is the entire set of activities S. The initial call, which solves the entire problem, is RECURSIVE_ACTIVITY_SELECTOR(s, f, 0, n).

RESURSIVE_ACTIVITY_SELECTOR(s, f, k, n)
  m = k + 1
  // find the first activity in Sk to finish (assumming orded by monotically increasing finish time)
  while m <= n and s[m] < f[k]:
    m = m + 1
  if m <= n:
    return { am } U RECURSIVE_ACTIVITY_SELECTOR(s, f, m, n)
  else return { }

The while loop looks for the first activity in Sk to finish, so that am is compatible with ak: such an activity has sm >= fk. If the loop terminates is because it finds such an activity. Alternatively, the loop may terminate because m > n, in which case, we havec examined all activities in Sk without finding one that is compatible with ak.

Iterative greedy algorithm

We can easily convert our recursive procedure to an iterative one, maintaining the same assumptions.

GREEDY_ACTIVITY_SELECTOR(s, f)
  n = s.length
  A = { a1 }
  k = 1
  for m = 2 to n
    if s[m] >= f[k]
      A = A U { am }
      k = m
  return A