Original file line number | Diff line number | Diff line change |
---|---|---|
|
@@ -27,73 +27,130 @@ below the estimate. These assumptions translate to risks - because if | |
they turn out to be incorrect, then they will add more time to the | ||
task. | ||
|
||
It's also possible to provide confidence intervals around an | ||
estimation to quantify the uncertainty. For example, a development | ||
task could be estimated to take 30 hours expected, +20 hours worst | ||
case, -5 hours best case. However even then, how often do we expect | ||
that actual time will come in longer than "worst case?" | ||
## Capturing uncertainty in our estimates | ||
|
||
## Story points estimates | ||
One common way to express an estimate for a given task is to give a single | ||
number: the number of remaining days of effort the task owner believes that he | ||
or she will require to finish that task. | ||
|
||
We accept that accurate estimation is hard, for multiple reasons, so | ||
instead adopt the "just in time" planning technique from XP. | ||
However, a single number alone is unable to capture the degree of confidence or | ||
uncertainty the author of an estimate has. To allow estimate authors to record | ||
their confidence or uncertainty, we need a bit more information. | ||
|
||
This uses unitless "story points" for estimation of each | ||
ticket. Possible story point values are on the Fibonacci sequence: | ||
1, 2, 3, 5, 8, 13. | ||
Therefore, we attach to each task a **pair** of estimates: | ||
|
||
The idea is that these point values represent task size in an abstract | ||
way. An estimate in time for a task can be calculated from the | ||
estimate in story points divided by the project velocity, adjusted | ||
according to staff availability, other factors, etc. | ||
- **Most-probable estimate (days)**: the number of remaining days of effort the | ||
task owner believes he or she will most likely need to finish that task. | ||
|
||
The decision on whether a task is included in the next sprint is | ||
based on its points estimate and the project velocity. | ||
- **Most-pessimistic estimate (days)**: the number of remaining days of effort | ||
the task owner believes he or she will need to be 90% of confident of | ||
finishing that task, given a pessimistic appraisal of the situation, and | ||
taking into account all of the potential things that could go wrong. | ||
|
||
This approach is clearly a **gross simplification of reality**, and so | ||
we need to be very careful not to produce garbage estimates. | ||
Note that it's impossible (in general) to predict all the things that could go | ||
wrong with a task. This is why estimates are estimates, and not commitments. | ||
Pilots and co-pilots should feel free to give estimates based on their personal | ||
experience. They may use their accumulated knowledge of how long similar tasks | ||
have taken in the past to develop new estimates. | ||
|
||
### Points | ||
The **deviation** between the most-probable estimate and most-pessimistic | ||
estimate allows the authors of each estimate to express their degree of | ||
uncertainty in the estimate, and it allows people viewing the estimates to gain | ||
insight into that uncertainty. | ||
|
||
| Points | Size | | ||
| -----: | ----------------------------------------------- | | ||
| 1 | | | ||
| 2 | | | ||
| 3 | | | ||
| 5 | | | ||
| 8 | | | ||
| 13 | | | ||
| > 13 | This ticket needs to be split up further. | | ||
A very large deviation between the most-probable and most-pessimistic estimate | ||
tells us that the author is very uncertain in their estimate. We might use | ||
this information to take action, for example, by breaking up a task into | ||
smaller, more well-defined pieces. | ||
|
||
### Each _Task_ ticket has an estimate | ||
It's important to realize that: | ||
|
||
We assign an estimation to every single task ticket. If there's no | ||
estimate, then it can't be added to the sprint. | ||
- These estimates pertain to the number of days of remaining effort required to | ||
perform that task **in isolation**. If two or more tasks are performed in | ||
parallel, with context switching, then we need to keep the additional cost of | ||
that context switching in mind. | ||
|
||
### Ticket must be ready to estimate before estimation | ||
- These estimates refer to a number of days **remaining**, and as such they | ||
There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. Interesting, will this prove problematic to the current JIRA system? I think it presumes estimates are unchanged from the initial estimate in it's velocity calculations etc. I don't really find those JIRA features useful anyway, so I don't really care, but might be worth running past Sergiy. |
||
should be regularly updated as circumstances change, rather that set in stone | ||
and left unchanged. | ||
|
||
If there is not enough information about a task ticket, then the | ||
estimation will be rubbish. So before estimation starts we need: | ||
## Guidelines for creating estimates | ||
|
||
1. The _Task_ ticket is linked to a _User Story_ ticket. | ||
2. The ticket description contains adequate information about what is | ||
expected to be done. | ||
3. The ticket includes acceptance criteria. | ||
4. The ticket is sufficiently small to estimate. | ||
5. Task dependencies are defined with jira issue links. | ||
- Estimates should only be created and updated by the pilot and co-pilot | ||
responsible for a given task. | ||
|
||
## Team Estimation | ||
- Estimates should be created only after a _Task_ ticket has entered the | ||
There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. I like this a lot. We should only consider adding tasks to a sprint that are in a READY state. But is this process documented anywhere else? If so, could we add a link to it? I haven't heard about the READY state before. There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. Yes, we should add a new page with our definition of ready, as it applies to estimation for task tickets. |
||
"READY" state. This means that a task should not be estimated if either the | ||
pilot or the co-pilot are unclear on what must be done. | ||
|
||
Story point estimations are done by the development team together in | ||
the [[Meetings|sprint planning meeting]]. | ||
This implies that: | ||
|
||
We use the [Pointing Poker](https://www.pointingpoker.com/) tool to | ||
facilitate estimation sessions. | ||
- The _Task_ ticket should have a complete set of acceptance criteria. | ||
|
||
The team should agree on a single number. If they don't then someone | ||
is missing some information about the task. | ||
- The _Task_ ticket should have a clear design that the pilot and co-pilot are | ||
capable of estimating. Justification: there are many possible designs for a | ||
given set of acceptance criteria. The time to deliver a task will depend very | ||
strongly on the design that is chosen. | ||
|
||
This practice lets us share knowledge about tasks. | ||
- The _Task_ ticket should be linked to a _User Story_ ticket, **if** it | ||
pertains to a user story. (It's important to note that not all tasks must | ||
have a corresponding user story. In the case of technical debt tasks or pure | ||
refactoring tasks, it might not be practical to even identify a user story.) | ||
|
||
- The _Task_ ticket is sufficiently small to estimate. | ||
|
||
- Task dependencies are defined with Jira issue links. | ||
|
||
## Process for updating estimates | ||
|
||
One of the main benefits of estimation is that both project management and other | ||
team members can gain visibility on how much time might be required to bring | ||
certain tasks to completion. | ||
|
||
Since we have one project planning meeting per week, it makes sense to update | ||
our estimates at around the same frequency. | ||
|
||
Before each project planning meeting (currently on Wednesday), each team member | ||
should: | ||
|
||
- Identify the tasks he or she is currently working on, in JIRA. | ||
|
||
- Make sure that each task has an updated pair of estimates that best reflect | ||
their current understanding of how much remaining time would be required to | ||
bring these tasks to completion. | ||
|
||
## Interpreting estimates | ||
|
||
Estimates do not represent commitments on behalf of those who create them. | ||
There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. Short but powerful 😄 |
||
|
||
The actual time required to finish tasks, when compared to initial estimates, | ||
can vary wildly, with some tasks taking many times longer than initially | ||
predicted. | ||
|
||
This factor: the actual time divided by the estimated time, is often known as | ||
the "blowup factor". | ||
|
||
There is some research to indicate that the "blowup factor" (actual time | ||
divided by estimated time) can be reasonably modelled using a log-normal | ||
distribution. See https://erikbern.com/2019/04/15/why-software-projects-take-longer-than-you-think-a-statistical-model.html | ||
|
||
TODO: | ||
|
||
- [ ] When we have a task with a chain of dependent tasks, devise an automated | ||
method of calculating a most-probable estimate and a most-pessimistic | ||
estimate for the entire chain of tasks. This method might use the log-normal | ||
distribution model suggested above in order to capture the possible blowup | ||
factor for the entire chain. | ||
|
||
- [ ] When we have a release that contains large numbers of tasks with | ||
There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. After reading the linked article, this sounds like it might prove useful for informing better commitment dates around intense bodies of work (like the PAB integration). I think we experienced (still are experiencing) pretty significant blowup factor for that work, which wasn't well represented by our initial estimates. |
||
dependencies between them, devise an automated method of determining the most | ||
likely critical paths required to deliver the release, and a method of | ||
calculating a most-probable estimate and a most-pessimistic estimate for | ||
delivering the entire release. | ||
|
||
In some situations, there will be one obvious critical path, but in more | ||
complex situations, there may be multiple contenders for the critical path, and | ||
the critical path may change as we make progress through a release. | ||
|
||
## Implicit acceptance criteria | ||
|
||
|
@@ -129,6 +186,38 @@ main task and linked. | |
We have found that Jira _subtasks_ aren't especially useful. They just | ||
make things confusing, so avoid using them. | ||
|
||
# Other methods of estimation | ||
|
||
## Story points estimates | ||
There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. I think this could do with some clarification: Are we continuing to use both story points and "most probable"/"most pessimistic" estimates? There was a problem hiding this comment. Choose a reason for hiding this commentThe reason will be displayed to describe this comment to others. Learn more. It seems like story points estimates are being relegated to the "Other methods" section. In any case it would be nice to add more detail to the story points section - e.g. transfer the info from Sergiy's presentation slide, give examples of 1,3,5 point tasks, etc. |
||
|
||
This method uses unitless "story points" for estimation of each | ||
ticket. Possible story point values are on the Fibonacci sequence: | ||
1, 2, 3, 5, 8, 13. | ||
|
||
The idea is that these point values represent task size in an abstract | ||
way. An estimate in time for a task can be calculated from the | ||
estimate in story points divided by the project velocity, adjusted | ||
according to staff availability, other factors, etc. | ||
|
||
The decision on whether a task is included in the next sprint is | ||
based on its points estimate and the project velocity. | ||
|
||
This approach is clearly a **gross simplification of reality**, and so | ||
we need to be very careful not to produce garbage estimates. | ||
|
||
## Team Estimation | ||
|
||
Story point estimations are done by the development team together in | ||
the [[Meetings|sprint planning meeting]]. | ||
|
||
This method can use the [Pointing Poker](https://www.pointingpoker.com/) tool | ||
to facilitate estimation sessions. | ||
|
||
The team should agree on a single number. If they don't then someone | ||
is missing some information about the task. | ||
|
||
This practice lets us share knowledge about tasks. | ||
|
||
## Updating estimations | ||
|
||
By rights, the estimation of a ticket should not change once the | ||
|
@@ -139,6 +228,19 @@ suggested, then the team velocity will decrease. The idea is that in | |
theory the velocity figure records under-estimation tendencies of the | ||
team, so that future sprints may be better planned. | ||
|
||
### Points | ||
|
||
| Points | Size | | ||
| -----: | ----------------------------------------------- | | ||
| 1 | | | ||
| 2 | | | ||
| 3 | | | ||
| 5 | | | ||
| 8 | | | ||
| 13 | | | ||
| > 13 | This ticket needs to be split up further. | | ||
|
||
|
||
## TODO: Put remaining time on ticket | ||
|
||
- [ ] Write process for updating tickets with "remaining time" value. |
There was a problem hiding this comment.
Choose a reason for hiding this comment
The reason will be displayed to describe this comment to others. Learn more.
I would prefer to stay well away from assigning numbers to confidence intervals. Terms like "quite" or "very" or "roughly" are far more appropriate I think.
Same goes with any pseudo-mathematical language, or using these numbers to calculate other estimates.
We simply do not have the historical data and estimation skill for that (... yet?).
There was a problem hiding this comment.
Choose a reason for hiding this comment
The reason will be displayed to describe this comment to others. Learn more.
I initially had the same feeling that the "90%" number in the confidence interval would merely give an illusion of precision, but after chatting with Jonathan, I have also come to believe that a more qualitative formulation like "very confident" does not capture the intent either.
The idea is this: Even though we may not (yet or ever) have the historical data or skill to estimate that number, stating that we want to estimate the "90%" confidence interval is something that we could, at least in principle, compare to historical data. Put differently: Even though my gut feeling for the pessimistic estimate will always be the number of days that I feel "very confident" about, the more precise "90% confident" qualifier encourages me to anchor the specific number of days to a timeframe were indeed, 90% of the time, I will have been historically able to finish the task in fewer days. The purpose of the confidence statement is not to reflect my own confidence about the number that I estimated here, but to reflect the timeframe for which my estimate is supposed to be — even though my estimate for that may just be a wild guess for the time being.
I will try to change the text to make this more clear. I do feel that the phrase "I'm 90% confident" is semantically not well-defined (feeling about my confidence VS unit of measurement).