Each iteration closes with an endgame.

Duties of the endgame champion

Proactive communication is key to a smooth and successful endgame.

  • Create the endgame plan and update the schedule (see template below and potentially last month's schedule)
  • Discuss the endgame plan in Monday's planning call
    • Find an endgame buddy in the other lab
    • Remind people to update their testing availability and platform(s) in the call and release channel
  • Communicate in the release Slack channel every day about the plan, progress, TODOs and any other important notifications.
    • Tidy up milestone (PRs, Issues, Feature Requests missing labels)
    • Availability of the insiders build
    • Testing to be done (Test Plan Items, Verifications)
    • Fixing Bugs / Candidates & Writing Documentation
    • Sanity testing and releasing.
  • Track progress and update the endgame plan by checking off the checklist items.
  • Coordinate with the buddy by communicating the progress and expected jobs to be done.
  • Adjust schedule, particularly the publishing dates, based on defects found, fixes made, holidays, vacations, etc.
  • Update the endgame process/template with the improvements/fixes that you learn in the current endgame.

Recovery Release

We release one or more recovery builds with a handful of critical fixes and translation updates a few days after a release. The candidate fixes are reviewed by the development team and are assigned to a recovery milestone. We want to be restrictive about the included candidates. The mindset is "we will lose users if we do not include the fix". Here are some examples:

  • data loss
  • a regression that users complain loudly about in issues or Twitter
  • a significant performance regression
  • an issue that impacts many users as indicated by telemetry data
  • an embarrassing UI glitch
  • critical security fixes (see Patch Tuesday Release Endgame Template below)
  • an issue that impacts extensions or is an API regression

Create Endgame Plan

Endgame champ can create the main and recovery endgame plans for a given milestone from the Endgame Duty website.

create-endgame-plan

This will create the endgame plan for the selected milestone. All you have to do after is to update the release and endgame dates.